Saturday, August 18, 2007

Progress Updates

  1. Drywall Finishing scheduled to start week of (8/20/07)
  2. Kitchen has been ordered- Species=Maple, Color= Coffee -----tentative delivery week of (9/17/07)
  3. Bathroom Cabinets have been Ordered -Color=White----tentative delivery week of (9/17/07)
  4. Interior Doors have been ordered. 6 panel white with satin hinges ---tentative delivery week of(9/3/07)